PREMIER Design + Build Group, LLC has finished the 2201 Lunt Ave. warehouse project in the industrial district of the village of Elk Grove, IL, reports Rejournals.com. The construction work began immediately after tearing down a previous structure in the area in summer 2013.

After Chicago-based Bridge Development Partners, LLC and Garland, TX-based Hillwood Investment Properties jointly purchased the land, the developers gave the management responsibility of the project’s design and build construction to PREMIER.

The 32-foot high facility features load-bearing precast construction on exterior wall panels and a glass curtain wall entryway. It also has 33 docks with airfreight user-accommodation capability and 185 parking spaces.

The warehouse has been equipped with an Early Suppression Fast Response (ESFR) fire protection system and an on-site retention pond and block retaining wall for stormwater management.

The facility can house up to four tenants. It enjoys easy accessibility to I-90, I-294 and O’Hare.

Elgin-based Wanxiang America Corp. was the capital partner, architectural work was done by Cornerstone Architects Ltd. of Austin, TX, and Rosemont, IL-based Spaceco Inc. served as the civil engineer.

The project manager was Mark Melone and the field superintendent was Johnathan Nelsen.