O’Hare breaks ground on $917-million Concourse E expansion

0
1

Chicago Construction News staff writer

Construction of a new 24-gate concourse at Chicago’s O’Hare International Airport is underway, with the $917-million project set to be delivered in two phases as part of the airport’s ORDNext modernization program.

Concourse E will add approximately 315,000 sq. ft. of passenger space and 14 gates in its first phase, followed by an additional 10 gates in a second phase, bringing the concourse to its full 24-gate capacity in 2034.The $640-million first phase is targeted for completion in 2030. The $277-million second phase will follow completion of the O’Hare Global Terminal, scheduled for late 2033.

Phase one will include domestic-capable gates, passenger holdrooms, nearly 21,000 sq. ft. of concession space and a public art program. The two-level concourse will extend more than 1,000 feet and connect to the New Concourse D through an underground passenger tunnel. Concourse D is scheduled to open in late 2028.

An updated construction sequence announced in August allows Concourse E and Concourse D to be built concurrently, providing additional gate capacity to support an accelerated schedule for the O’Hare Global Terminal, which is expected to begin construction in 2029 and be completed in a single coordinated phase by late 2033.

The design, led by Skidmore, Owings & Merrill (SOM) in collaboration with Ross Barney Architects, Juan Gabriel Moreno Architects (JGMA) and Arup, builds on the architectural approach developed for Concourse D while incorporating elements inspired by Chicago and the Midwest landscape.

The concourse will feature light-filled spaces, expanded passenger seating and concessions. Its southern end will include a curtain wall system designed to be relocated and reused when the second phase extends the building by 10 gates, minimizing disruption to airport operations.

The project also includes installation of a utility loop sized to accommodate the full 24-gate concourse and its projected capacity.

Construction is being led by the AECOM Hunt Clayco Bowa joint venture, with Connect Chicago Alliance serving as program manager for ORDNext, coordinating planning, design and construction across the airport modernization program.

The Concourse E groundbreaking follows ongoing work on Concourse D, where vertical construction is underway on the 19-gate facility. In June, a guaranteed maximum price of $1.455 billion was finalized for Concourse D, $21 million below its initially approved budget. The project remains scheduled for completion in late 2028.